Send Project Details

Why do office fit-outs fall behind schedule?

The visible work may be straightforward. What takes time is getting several decisions, services and specialist contractors to line up. A change to one part of the floor can affect drawings, procurement and installations elsewhere.

See How We Deliver

A small change can have a wide effect.

Move a meeting room and the power points, air-conditioning, acoustic treatment and cabling may all move with it. Close a ceiling before the last service has been installed, and completed work may need to be reopened. The problem is not always the individual trade; it is the sequence between trades.

Six common coordination problems.

These are practical questions to resolve before execution.

ProblemBetter planning response
Teams working from different drawingsMaintain an approved, controlled drawing set.
Services not aligned with room layoutsCoordinate electrical, HVAC, data and AV with the agreed layout.
Building restrictions found too lateConfirm landlord rules, approvals, lifts and work windows early.
Long-lead items identified after mobilisationRelease procurement from approved specifications and a lead-time plan.
Changes decided informallyRecord the revised scope, price and programme effect before execution.
Work handed over with unclear statusDefine completion checks, records and the treatment of outstanding snags.

What coordination can, and cannot, control.

WurkSpaces can manage its contracted work and coordinate agreed interfaces. It cannot independently approve a landlord drawing, release a client decision or force a third-party vendor to meet its deadline. Good project controls make those dependencies visible so decisions can be taken earlier.

Want to understand your own project dependencies?

Use the free Planner to list the requirements and unknowns, or send us the information you already have for an initial discussion.

Build My Office Readiness PlanSend Project Details